Network Rail has today apologised after admitting that it failed to spend £65 million of funding allocated to improving access at rail stations.
The admission came after Disability News Service (DNS) secured figures through a freedom of information request which showed spending on the Access for All scheme over the last eight years.
Network Rail – which owns, repairs and develops the railway infrastructure in England, Scotland and Wales – had originally delayed releasing the figures until after the general election, claiming this was due to “the complexity and volume of the information requested”.
But the figures show for the first time how spending on improving access at rail stations has fluctuated wildly over the last eight years, while £65 million allocated for improvements over the last five years has been left unspent.
The figures show that spending fell to as little as £15 million in 2017-18 but rose to more than £120 million last year.
Despite that increase, the figures show that the Department for Transport (DfT) allocated £350 million for 2019-2024, but only £285 million was spent over those five years.
Access for All was launched by the last Labour government in 2006, and funds access improvements at stations across England, Scotland and Wales.
The figures released to DNS by Network Rail show that spending rose from just £19 million in 2020-21, to £50 million the next year, then £66 million in 2022-23 and £121 million last year.
Despite the increases, £65 million of the £350 million allocated to the scheme – nearly 20 per cent – has not been spent over the last five years.
It is not yet clear how much the new Labour government plans to spend on Access for All over the next five years, or what action it will take over the unspent funding.
The figures also show that – in six of the last eight years – spending on improving access at rail stations was lower under Conservative-led governments than in the last year of the last Labour government (2009-10, when it was £54 million).
Apart from the £81 million spent in 2013-14, it is only in the last two years that annual Access for All spending has risen above £54 million since Labour left power.
The freedom of information release also confirms that DfT allocated £135 million for the scheme across the years 2014-19, but this was cut to just £87 million following a report in 2016 by the chair of Network Rail, Sir Peter Hendy.
That report called for £50 million in funding to be carried over to the next five-year period, 2019-24.
Hendy, now Lord Hendy, is Labour’s new rail minister – with responsibility for rail accessibility* – in the House of Lords.
A Network Rail spokesperson said this morning (Thursday): “Access for All schemes are so important to making rail travel easy for everyone and we are so sorry we have not delivered what we promised.
“We have experienced challenges with some of the more complex improvements, which means some schemes have taken longer than planned, and we were not able to spend all of the funding in the last five years.
“We have carried out a comprehensive review into the programme and we will complete the schemes as soon as we can.”
Caroline Stickland, chief executive of the disabled-led campaigning organisation Transport for All (TfA), speaking before Network Rail’s admission on the unspent funding, said: “Currently, Access for All funding is allocated through competitive bids and bidding wars.
“It’s time consuming and ineffective – and it appears that the last set of funding wasn’t fully spent.
“Access for All grants have made more rail stations accessible for more people, and that’s great, but the funding is not enough to bridge the transport accessibility gap on rail, meaning disabled people can’t use trains as much as non-disabled people.
“Most disabled people – roughly one in four of the UK population – are either unhappy or extremely unhappy about making journeys.
“That should make any government stop and think.
“Transport for All calls on the Department for Transport to increase funding for making stations accessible, make sure investment gets to where it’s needed to benefit disabled people, and make sure funds are spent quickly and effectively so that more of the transport system becomes accessible to all.”
Julian Vaughan, chair of Bedfordshire Rail Access Network, a train driver, and a Labour parliamentary candidate in 2017 and 2019, said Network Rail’s freedom of information response had revealed “the meagre and wholly inadequate government funding for accessibility on the UK rail network”.
Also speaking before Network Rail’s admission, he said he was concerned that Network Rail was not able to confirm the funding for the next five-year “control period”, from 2024-29.
He said: “There needs to be a complete culture change around accessibility on our public transport, which too often is seen as a favour, not as a right.
“Investing in an accessible rail network is not just morally the right thing to do, it makes sound economic sense too.
“The new Labour government has to date been silent on how they are going to improve accessibility across our rail network.
“I would urge them to set out a roadmap for the rollout of accessible stations and to involve disabled people at every stage of railway station improvements.”
He said Network Rail continued to fail disabled people.
Vaughan also said that some stations awarded Access for All funding in 2014 were still waiting for step-free improvements, which he said was “inexcusable”.
In 2022, a report by the government’s advisers on accessible transport, the Disabled Persons Transport Advisory Committee, concluded: “At current annual rates of investment spend on station accessibility, it will take around 100 years to make the entirety of the station estate step-free to new-build standards.”
And two years ago, rail operators told a research organisation that only “major” government funding would solve the accessibility problems at stations across the country.
*Local transport minister Simon Lightwood has been given responsible for local transport accessibility and “cross-cutting transport accessibility”
Picture by Office of Rail and Road
A note from the editor:
Please consider making a voluntary financial contribution to support the work of DNS and allow it to continue producing independent, carefully-researched news stories that focus on the lives and rights of disabled people and their user-led organisations.
Please do not contribute if you cannot afford to do so, and please note that DNS is not a charity. It is run and owned by disabled journalist John Pring and has been from its launch in April 2009.
Thank you for anything you can do to support the work of DNS…

DWP forced to release report that includes ‘outrageous’ revelation about sub-standard assessment reports
Slow but steady progress on UK air travel access improvements, says report
Information Commission orders DWP to release secret report that examined quality of PIP phone assessments